A key federal mine reclamation program is up for reauthorization in 2021 — and the work is far from finished
Kevin Ridder | February 15, 2018 | No Comments
The AML program, which was established by the Surface Mining Control and Reclamation Act of 1977, was the first regulatory step toward fixing the slew of the coal industry’s leftover messes. Even under current law, however, pollution problems from newer and older mines persist.
The federal agency then distributes annual payments to states and tribes based on a complex formula involving the amount of coal each state and tribe currently produces and the amount produced before 1977. The U.S. Department of the Interior states that roughly $4.3 billion has been disbursed for reclamation projects and around $2.5 billion has been distributed for other uses. In Appalachia alone, the AML program supported 3,762 jobs in fiscal year 2017 and had an estimated economic impact of over $378 million in the region.
“The size of the remaining problem is very shocking,” says Eric Dixon with the Appalachian Citizens’ Law Center, a nonprofit law firm. “It will take us many years, many decades at our current rate, to clean up all of the abandoned coal mines that fall under this program. And those are only the coal mines that were abandoned prior to 1977.”
Fees paid by coal companies have not risen alongside 41 years of inflation. Additionally, payments from the AML fund were subject to the annual congressional budget process until 2006 — meaning Congress underallocated AML funds to states and tribes for years. Full annual payments are now mandatory, and Congress disbursed funds to states and tribes to account for the majority of the historical unpaid balance.
Allocations to states and tribes have fallen since 2013 due to sequestration, which is projected to create a total loss of $136 million in AML fund payments to states and tribes through 2021.
“Sequestration has caused less money to be delivered to states to clean up coal mines and do this important work,” says Dixon, who co-authored an extensive policy analysis of the AML program in 2015. “And a lot of people have issue with that because the money that funds these cleanups isn’t general taxpayer money, it’s money that was collected from the coal industry over the past 40 years and continues to be collected on an annual basis.”
Calls to accelerate Appalachian mine remediation resulted in the creation of the AML Pilot Program in 2016, which authorized annual payments from the U.S. Treasury, not the AML Fund, to three Appalachian states and then six in 2017. The RECLAIM Act, a bill that would disburse $1 billion from the AML Fund’s unappropriated balance over five years instead of waiting until 2023, passed the House Natural Resources Committee in June. The bill’s supporters — including Appalachian Voices, the publisher of this newspaper — are urging both chambers of Congress to vote on the House’s version of the RECLAIM Act, H.R. 1731, in early 2018.
Information available to the public through the OSMRE’s online Abandoned Mine Land Inventory System — from which much of the data on these graphics is sourced — is limited. It only includes abandoned mines that have been catalogued by the federal government, and problems that affect the environment but not human health are not required by law to be listed.
“There are many, many, many more abandoned coal mine problems throughout this country than will be cleaned up by the current sunset date of 2021,” says Dixon. “So it is imperative that we reauthorize the program and that we clean up these coal mines that are impeding economic development and are affecting public health.”
Editor’s Note: This story was updated on March 8 to include the unappropriated balance of $2.44 billion left in the Abandoned Mine Land Fund, the effects of sequestration on the program and the economic impact of the program in fiscal year 2017.
West Virginia’s Cheat River is currently a favorite for whitewater enthusiasts and anglers alike.
In the summer of 1988, so much acid mine drainage from abandoned and active coal mining operations had built up in the river that the water ran orange.
Today, the Cheat watershed is in a much better state, thanks largely to Friends of the Cheat and funding from a variety of sources including the Abandoned Mine Lands program. AML funds have also helped the West Virginia Department of Environmental Protection undertake nearby land reclamation projects that have improved downstream water quality.
“It’s unbelievable the comparison between what the river looked like then and what it looks like now, just 30 years later,” FOC Executive Director Amanda Pitzer says.
“For the future, I can’t say I have an answer if we don’t get [AML program] reauthorization or something that looks like it,” she says.
Like this content? Subscribe to The Voice email digests